Maintenance dredging

From 1996 maintenance dredging of around 100,000 cubic metres has occurred every year, with the disposal of material placed at the East Banks offshore site.  The volume of maintenance dredging varies depending on the siltation that has settled in the existing channels and berths.

 

Capital dredging projects


Date        
Location
Depth
Volume
Dredge Type
Disposal Site

1960-66

Auckland Point berths, Barney Point berths and harbour channel

Auckland Point: 23ft
Barney Point: 39ft
Harbour channel: 9.6m

A significant volume

  

1968

Entrance channel

10.4m

Further deepening

  

1980-82

Approach channels to Clinton and Fisherman's Landing, as well as the Marina

 

20 million cubic metres

Trailer / Cutter

Sea / ashore

1986-87

Inner harbour channels widened and berths deepened

Auckland channel widened to 180m and deepened to 15m

3 million cubic metres

Trailer / Cutter

Ashore

1987

Outer channel

15.8m

2.5 million cubic metres

Trailer / Cutter

Sea

1997

Fisherman's Landing

 

1 million cubic metres

  

1997

Outer channel

16.3m

1 million cubic metres

Trailer

Sea

1998

Inner channel swing basin

 

2 million cubic metres

  

1999

Inner channel

 

2 million cubic metres

Trailer / Cutter

Ashore

2001-03

Berth 3 at RG Tanna Coal Terminal and Fisherman's Landing including deepening of Targinie Channel and Clinton Bypass Channel

 

2 million cubic metres

Trailer / Cutter

Ashore

2005

RG Tanna Coal Terminal berth 4

 

0.75 million cubic metres

Cutter

Ashore

2008-09

Fisherman's Landing berth pocket and approach

 

0.66 million cubic metres

Cutter

Ashore

2009-10

Gladstone Marina

 

350,000 cubic metres

Trailer / Cutter

Ashore

2010-11

Early works access to Curtis Island

 

375,000 cubic metres

 Cutter

Ashore 